Bright Home Energy

Timelines

All timelines are business days

StageBH SLATotal Days (working days)
Conversion1 DayDay 1
Site Visit2-3 DaysDay 4
Site Visit Review1 DayDay 5
Design3 DaysDay 8
Design Review1 DayDay 9
HO Design Review1 DayDay 10
Permit/Utility Submission1-2 daysDay 12
*Additional HO signatures required at this time
Permit CompletionN/ADay 13-34 AVG
*Varies based on scope of work – AVG 1-3 weeks
Utility CompletionN/ADay 13-34 AVG
*Varies based on scope of work – AVG 1-3 weeks
Ready For Install1-3 Days
Install1 DayUnder 45 days
*Varies based on scope of work – AVG 1-3 days
City Inspection1 Day
Utility Greentag1 Day
Permission To OperateN/AUnder 60 days

** Batteries, Ground Mounts, and 400A panels may add up to 7 more business days.

Efficiency scheduling will begin once permits are received.

Birdwire scheduling will begin once we've passed City Inspections.